Ghana deaf ed mission projects

SAMAS CONSTRUCTION WORKS LIMITED (CIVIL ENGINEERING AND BUILDING WORKS)

CONSTRUCTION OF ASTROTURF WITH TARTAN TRACKS FOR THE AKUAPEN SCHOOL OF THE DEAF BILL OF QUANTITIES

ITEM DESCRIPTION UNIT QTY RATE GH AMOUNT GH
BILL NO.1 GENERAL ITEMS
A
Preliminaries
75,000.00
PRELIMINARIES: Total carried forward to Summary
75,000.00
ITEM DESCRIPTION UNIT QTY RATE GH AMOUNT GH
BILL NO.2 THE WORKS ASTROTURF WITH TARTAN TRACKS
A
Demolish block and concrete structures and remove from site
m3
146
182.00
26,572.00
B
Fell and remove trees girth 1m - 2m
nr
2
860.00
1,720.00
C
Excavate topsoil, maximum depth not exceeding 250mm and dispose
m3
1,040
94.00
97,760.00
D
Provide, spread and camped imported fill material as turf base, maximum thickness not exceeding 500mm
m3
770
142.00
109,340.00
E
Provide and install 150mm diameter perforated pipes for subsurface drainage. including all accessories
m
580
178.00
103,240.00
F
Provide, spread and compact 1Omm granite membrane for subsurface drainage, maximum thickness not exceeding 200mm
m3
510
242.00
123,420.00
G
Provide and lay 20rnin HD foam layer over compacted granite layer
m2
2550
62.00
158,100.00
H
Provide and install artificial turf including all accessories and markings
m2
1640
147.00
241,080.00
I
Provide and install galvanized steel goal posts with nets
nr
2
8,800.00
17,600.00
J
Provide and install 3-in-1 steel chairs as players' bench seats with steel canopy
nr
4
10,240.00
40,960.00
K
Provide and Install chain link fence with 100mm galvanized steel posts including all accessories
m
210
926.00
194,460.00
L
Provide and place C20/25 mass concrete kerbing for boundary definition and protection of turf edges, thickness not exceeding 150mm
m
516
48.00
24,768.00
M
Provide and install artificial tartan tracks including all accessories and markings
m2
910
262.00
238,420.00
N
Mow for a sum of GH₵ 60,000.00 for the provision and installation of lighting systems and fittings
Item
60,000.00
O
Provide and place C30/25 reinforced concrete in stands. including formwork
m3
260
1,225.00
318,500.00
P
16mm diameter high yield bars in concrete stands
ton
21
9,950.00
208,950.00
Q
Allow for a sum of GH₵ 350,000.00 for the fabrication and installation of steel canopies for stands, including spraying
Item
350,000.00
R
Allow for a sum of GH₵ 50,000.00 for the provision and installation of plumbing systems and fittings
Item
50,000.00
S
Allow for a sum of GH₵ 140,000.00 for the provision and furnishing of 2 dressing rooms
Item
140,000.00
T
Allow fore sum of GH₵ 200,000.00 for the refurbishment of existing basketball court
Item
200,000.00
ASTROTURF WITH TARTAN TRACKS:Total carried forward to Summary
2,704,890.00

SUMMARY

ITEM DESCRIPTION UNIT QTY RATE GH AMOUNT GH
A
Preliminaries
75,000.00
B
ASTROTURF WITH TARTAN TRACKS
2,704,890.00
TOTAL WORKS
2,779,890.00